Concrete Restoration Bid Package: How Condo Boards Get Comparable Repair Bids
A concrete restoration bid package puts every contractor on the same scope, the same estimated quantities and the same repair methods. It’s how a board turns a milestone report into repair prices it can compare.
- Licensed professional engineer in Florida
- Signed and sealed reports
What a Concrete Restoration Bid Package Is, in Short
A concrete restoration bid package is the set of documents your engineer prepares so contractors price the same repairs. It typically includes signed and sealed repair drawings, specifications, and a bid form with estimated quantities and unit prices. Without one, you’re usually comparing prices for different scopes of work, and nobody can tell you which is the better deal.
Your milestone report tells you what’s wrong and recommends repairs. It isn’t written for a contractor to build from. The bid package is the step in between, and the same signed and sealed drawings are generally what the building department reviews when the contractor applies for a permit.
If you’re still working through the report itself, start with our phase two guide. If the report is done and the board is asking you for prices, keep reading.
Why Bids from an Inspection Report Don't Match
Here’s what usually happens. The report lands, the board asks the manager for three prices, and the report goes out to three contractors. The numbers come back far apart, and the board assumes somebody is overcharging.
Usually nobody is. When you ask contractors to price straight from a report, each one makes its own assumptions about scope, quantities and repair methods. One prices only the locations the report names. Another walks the building and adds what they expect to find. A third includes an allowance for damage nobody has seen yet. Those are three different jobs.
Concrete makes this harder than most trades. The true extent of deteriorated concrete and corroded reinforcing steel often isn’t known until the concrete is removed. A contractor guessing at hidden damage either adds money for it or leaves it out, and you can’t see which from the total.
None of this is a flaw in the report. Under the milestone inspection statute, the report has to identify substantial structural deterioration, describe its extent and recommend repairs. Our milestone inspection report guide explains how to read those recommendations. Turning them into something a contractor can price is separate engineering work.
What Goes into a Concrete Restoration Bid Package
Packages vary with the building, but a well-prepared one typically has six parts.
Signed and Sealed Repair Drawings
Plans and details showing the known repair areas, how each type of repair is built, and how extra damage found during removal gets handled. Under Florida law, the final drawings and specifications an engineer gives the owner or files for public record must be signed, dated and sealed.
Technical Specifications
The written requirements for materials, surface preparation, workmanship and testing. They give every bidder the same technical basis, and they're what the work gets checked against later.
Bid Form with Estimated Quantities
A schedule that lists each repair type with the engineer's estimated quantity and a blank for the contractor's unit price. Everyone fills in the same lines, so you can compare the bids line by line.
Scope and Phasing
What's included, what isn't, and the order the work happens in. On an occupied building, phasing decides which areas are out of service and when.
Access and Protection Requirements
The access limits and protection the contractor has to price for occupied areas, such as where equipment can be staged and how walkways and parked cars are protected.
Bidder Qualifications
What the association asks bidders to show, such as licensing, insurance and experience with similar concrete repairs. It lets the board compare companies along with prices.
Three Ways to Ask for Repair Prices
How you ask for prices decides what you can compare afterward.
| Approach | What each contractor prices | When hidden damage shows up |
|---|---|---|
| Send the report to contractors | Its own reading of the report, with its own quantities and methods | Each bidder assumed something different, so the extra cost is hard to predict |
| Lump sum from the engineer’s drawings | One total for the work shown on the drawings | Damage beyond the drawings may fall outside the priced scope |
| Unit prices on the engineer’s bid form | The same repair types and estimated quantities, line by line | Payment typically adjusts to the measured quantities at the unit prices already bid |
How Unit Prices Handle Hidden Damage
Concrete restoration is commonly bid with estimated quantities and unit prices for each repair type, for example per square foot of slab repair or per linear foot of crack repair. The engineer estimates how much of each repair the building needs. Every contractor prices that same list. In contract terms, it’s a unit price contract.
When the concrete is opened up and the damage turns out larger or smaller than estimated, the price per unit doesn’t change. The quantity does. The engineer typically measures or verifies the repaired quantities, and the contract sets how payment follows them.
It isn’t a perfect system. Your final cost still moves with what’s found, and the board should hear that before the vote, not after. It also belongs in your condo reserve funding conversation. But the board knows the rate for every extra square foot before it signs, and that’s a far better position than negotiating each surprise in the middle of the job.
How Bidding Usually Runs
The steps are much the same on most condo repair projects.
The Engineer Prepares the Package
Working from the milestone report and any testing, the engineer prepares the repair drawings, specifications and bid form.
01
The Association Invites Licensed Contractors
The package goes to licensed contractors who do concrete restoration, with a due date and the qualifications you’re asking for.
02
Pre-Bid Site Walk
Bidders walk the property so they all see the same access and site conditions. The walk won’t reveal concealed damage, which is what the unit prices are for.
03
Questions Answered in Writing
Contractors send questions to the engineer, and the answers go to every bidder in writing. No one prices from a private conversation.
04
Bids Come Back on the Same Form
Each contractor fills in unit prices against the same estimated quantities.
05
The Engineer Reviews the Bids
The engineer lays the bids side by side for the board and points out exclusions, qualifications and prices that look out of line.
06
The Board Selects a Contractor
The decision is the board’s. For condominium associations, Florida’s bidding law doesn’t require you to accept the lowest bid.
07
Permit, Then Repairs
The contractor applies for the permit, and work starts once it’s issued.
08
Florida Rules to Check Before You Award
Start with the clock. Each county or city has to adopt an ordinance that makes associations schedule or commence repairs for substantial structural deterioration within a set time after the local enforcement agency receives a phase two report. State law sets the outer limit: the repairs must be commenced within 365 days after the report is received.
If the owner doesn’t submit proof to the agency that repairs have been scheduled or have commenced within the required time, the agency must review and determine whether the building is unsafe for human occupancy. Ask your building department what its ordinance requires and what proof it accepts.
Next, bidding. For condominium associations, the competitive bids statute says contracts for materials, equipment or services must be in writing. The association must obtain competitive bids when a contract’s total payments exceed 5 percent of the association’s total annual budget, including reserves. Check a structural repair contract against that line early.
The same statute doesn’t require you to take the lowest bid, and it doesn’t limit what the association can do in an emergency. Associations with 10 or fewer units can opt out by a two-thirds owner vote. Contracts for engineering services aren’t subject to it, so it’s normally the repair contractor’s contract that triggers bidding, not the engineer’s.
Last, a disclosure rule many boards haven’t heard of. An architect or engineer who bids to perform a milestone inspection must tell the association in writing if they intend to bid on maintenance, repair or replacement services the inspection may recommend. A design professional or licensed contractor who bids on recommended services must disclose in writing any direct or indirect interest in the inspection firm, or a family relationship with someone who has one. Without the required disclosure, the contract is voidable and ends when the association files a written notice terminating it.
Ask for those disclosures from anyone who inspected your building and now proposes repair-related work, our firm included. Our Florida milestone inspection law page covers more of the statute, and the board’s attorney should confirm how these rules apply to your association.
Permits, Special Inspection and the Engineer's Role During Repairs
Building departments generally require a permit for structural concrete repairs and review signed and sealed drawings. Requirements differ by city and county, so confirm the submittal list with your own building department before bids go out.
Taller buildings have one more layer. Under Florida law, a threshold building is one greater than three stories or 50 feet in height, and certain large assembly buildings also qualify. When a repair or restoration project modifies the structural system or structural loading of a threshold building, the enforcing agency requires a special inspector. That inspector performs structural inspections under a plan prepared by the engineer or architect of record. The owner selects and pays the special inspector, who is responsible to the enforcement agency.
Your building department will tell you whether your project needs one. If it asks for a special inspector letter, our page on that document explains what it is.
During construction, the engineer typically reviews the contractor’s submittals, observes the work at agreed stages, verifies repair quantities and issues a completion letter at the end. Ask your building department what it needs to close the permit.
One thing to be clear about. Milestone Inspections US, led by Paul Edwards Pineda, PE, who has 22 years of experience, inspects, diagnoses and prepares the plans and the bid package. We answer contractor questions during bidding, review the bids and stay involved during construction. We don’t perform repairs, and we have no financial relationship with any contractor. The association hires its own licensed contractor. If that’s the help you need, our concrete restoration engineering page describes the service, or call 305-890-6333.
What a Property Manager Can Get Ready Now
You don’t have to wait for a board vote to start. Having these in hand saves time once the engineer begins.
- The full milestone inspection report, the inspector's summary and any test results.
- Original structural or architectural drawings, if the association has them, and records of earlier concrete repairs.
- A list of known problem spots with photos and locations: spalled concrete, cracks, rust stains, leaks.
- The current reserve study and funding plan, since repair timing and cash flow drive the board's choices.
- Your local ordinance's repair deadline and what the building department accepts as proof that repairs are scheduled.
- Who on the board can approve the engineer's proposal and, later, the contractor award.
- Access and staging limits: parking, entrances and how residents will be notified.
- One point of contact for contractor questions, and a simple log of board decisions.
Frequently Asked Questions
A bid package is the set of documents sent to contractors so they can price a job: drawings, specifications, a bid form and instructions to bidders. For condo concrete repairs, the engineer typically prepares it so every bid covers the same scope.
If you want prices you can compare, in most cases yes. The report recommends repairs, but it usually doesn’t give contractors the drawings, specifications or quantities they need to price line by line.
You can, but the prices will likely be for different scopes, so the lowest number isn’t necessarily the lowest cost. For condominium associations, Florida’s bidding law doesn’t require accepting the lowest bid in any case.
Contractors price the same repair types and estimated quantities on the same bid form. When concrete is removed and the real extent is known, the engineer typically verifies the quantities and payment follows the unit prices already in the contract.
No. We inspect, prepare the signed and sealed plans and bid package, and provide engineering services during construction. The association hires a separate licensed contractor, and we have no financial relationship with any contractor.
When the building is a threshold building and the project modifies its structural system or structural loading. The enforcing agency then requires a special inspector working under a structural inspection plan. Confirm with your building department whether your project falls under that rule.