Milestone Inspections in Palm Beach County: What Condo Boards Need to Know
Condo boards face different milestone inspection procedures depending on whether the building is in unincorporated Palm Beach County or a city with its own building department. This guide explains Palm Beach County milestone inspections that boards must plan for, from age triggers to inspection phases and repair deadlines.
- Licensed professional engineer in Florida
- Signed and sealed reports
Palm Beach County Milestone Inspections: County Rules vs City Rules
For Palm Beach County milestone inspections, boards must first identify the building department responsible for their property. In unincorporated Palm Beach County, covered condo and co-op buildings follow the county program, with first inspections at 25 or 30 years depending on coastline distance. Cities such as Delray Beach, Boca Raton and West Palm Beach run their own programs, so confirm local requirements with the city building department.
The Palm Beach County building department page covers condo and co-op buildings three stories or taller in unincorporated Palm Beach County. For a statewide overview, see milestone inspections in Florida.
The Florida milestone inspection law applies to buildings three habitable stories or more in height. The building must be subject in whole or in part to residential condominium or residential cooperative ownership.
It does not apply to single-family, two-family, three-family or four-family dwellings with three or fewer habitable stories above ground. The core state rule is in s. 553.899, Florida Statutes.
The county page also notes that reports are uploaded through the county online portal, ePZB, by the architect or engineer who prepared them. A Building Reference ID is needed. For city programs, confirm the upload path with the city building department.
The local enforcement agency runs the inspection process. The board should not rely on a neighboring building’s letter or portal instructions without checking jurisdiction.
Identify the responsible building department before planning the submission. Keep its instructions with the building records so future board members can follow the same process.
25 Year vs 30 Year Triggers in Palm Beach County
The first inspection year can differ by location. Use this table to separate the county rule from city rules, then confirm your building’s specific date with the right building department.
| Item | Unincorporated Palm Beach County | Cities with Their Own Building Department |
|---|---|---|
| Who enforces the program | Palm Beach County building department | The city building department |
| First inspection trigger | Within 3 miles of a coastline: 25 years. More than 3 miles: 30 years. Every 10 years after. | Confirm with the city. Do not assume the county age trigger applies. |
| Notice | Associations receive certified letters in the year an inspection is due. | Confirm the local notice procedure with the city. |
| Report upload | ePZB, by the architect or engineer who prepared the report. A Building Reference ID is needed. | Confirm the submission method with the city. |
| State authority for an earlier trigger | The local enforcement agency may require inspection at 25 years where local circumstances, including proximity to salt water, call for it. | The local enforcement agency may require inspection at 25 years based on local circumstances. Confirm the applicable trigger with the city. |
The Certified Letter and the 180 Day Window
For Palm Beach County milestone inspections, boards should track the written notice and the 180 day window. The local enforcement agency sends written notice when an inspection is due. Phase one must be completed within 180 days of that notice.
In unincorporated Palm Beach County, associations receive certified letters in the year an inspection is due. Keep the notice with the inspection records and share it with the engineer.
The local enforcement agency may extend the deadline for good cause. The owners must have a contract with an engineer or architect, and the inspection must be unable to be completed in time.
The extension is not automatic. The board should ask the building department what documentation it requires for good cause. The local agency decides whether to grant the extension.
The first milestone inspection is due by December 31 of the year the building reaches 30 years of age, unless an earlier local trigger applies. Age is based on the certificate of occupancy date. Inspections follow every 10 years.
Buildings that reached 30 before July 1, 2022 were due before December 31, 2024. Buildings reaching 30 between July 1, 2022 and December 31, 2024 were due before December 31, 2025.
For a county by county view of dates, review deadlines by county. Confirm your building’s applicable deadline with the local enforcement agency rather than treating the notice window as a replacement for the age-based schedule.
How Phase One and Phase Two Work
The inspection process begins with jurisdiction and records, then moves through the required examination and any follow-up work. Phase two is not required for every building.
Confirm Jurisdiction and Due Year
The board checks whether the building is in unincorporated Palm Beach County or a city with its own building department. It also confirms the certificate of occupancy date and whether the 25 year or 30 year trigger applies.
01
Receive Written Notice
The local enforcement agency sends written notice. Phase one must be completed within 180 days of that notice. Give the engineer the notice so the inspection can be planned around the applicable deadline.
02
Complete Phase One
A Florida-licensed architect or engineer performs a visual examination of habitable and non-habitable areas, including major structural components. The professional gives a qualitative assessment. A team may be used, but reports are signed and sealed by the responsible qualified professional.
03
Review Phase One Findings
If phase one finds no signs of substantial structural deterioration, phase two is not required. Surface imperfections include cracks, sagging, leaks and peeling finishes. They are excluded from substantial structural deterioration unless the engineer or architect determines they indicate it.
04
Complete Phase Two If Required
Phase two is required if phase one finds substantial structural deterioration. It may involve destructive or non-destructive testing. Our phase two guide explains what boards can expect.
05
Start Required Repairs on Time
Repairs for substantial structural deterioration found in a phase two report must commence within 365 days after the local enforcement agency receives the report. Track that receipt date rather than using the date a contractor provides a bid.
06
What to Prepare Before the Engineer Arrives
Preparation helps the engineer understand the building and helps the board answer questions later. Organize available records and discuss access needs before the visit.
Certificate of Occupancy Date
The inspection age is tied to the certificate of occupancy date. Keep a copy where the board and manager can find it. If the date is unclear, ask the building department how to confirm it.
Prior Inspection and Repair Records
Gather past reports, permits, repair drawings and closeout records. The engineer can use them to understand the building's history. Identify missing records rather than assuming earlier work resolved a current concern.
Access Plan
Discuss access to roofs, parking areas, balconies, stairwells, mechanical rooms and unit interiors where needed. Give the engineer a single point of contact. Confirm the areas needed for the examination before notifying owners.
Board Contact and Decision Path
Decide who will receive the report, who will call the engineer and who will update owners. Keep questions together so the board can discuss findings without relying on secondhand explanations.
Budget and Reserve Context
If repairs may follow, review the SIRS and reserve study with the manager. The board should understand available funds when discussing repair planning. Do not treat reserve information as a substitute for the engineer's structural findings.
Upload Details
For the county program, the architect or engineer who prepared the report uploads it through ePZB. A Building Reference ID is required. Confirm that identifier with the county before submission.
Communication with Owners
Tell owners what a milestone inspection is and when the engineer will need access. Explain that phase one findings determine whether phase two is required. Share confirmed information rather than predicting the inspection outcome.
Repairs After a Phase Two Report
A phase two report can change the board’s repair planning. The 365 day requirement concerns commencing repairs for substantial structural deterioration, not completing them. Its clock begins when the local enforcement agency receives the report.
Boards should account for design, permitting and construction when discussing the next steps. Ask the engineer to explain the findings and proposed repair scope before seeking contractor proposals.
For a threshold building, repairs or restoration that modify the structural system or structural loading require a special inspector under s. 553.79(5). The enforcing agency requires structural inspections under a plan prepared by the engineer or architect of record.
The structural inspection plan must be submitted to and approved by the enforcing agency before the building permit is issued. The fee owner selects and pays the special inspector, but the special inspector is responsible to the enforcement agency.
A threshold building is any building greater than three stories or 50 feet in height. The definition also includes an assembly occupancy over 5,000 square feet with an occupant content over 500 persons.
An owner of a building below the threshold criteria may voluntarily designate it a threshold building. For repair planning, boards should ask the engineer whether threshold inspection requirements apply.
Special inspections do not replace the building official or the architect or engineer of record. They also do not relieve the contractor of its obligations.
Paul Edwards Pineda, PE does the work for Milestone Inspections US. He is a Florida-licensed Registered Structural Engineer with 22 years of experience. Reports are signed and sealed by the responsible qualified professional.
Board Checklist for the Inspection Process
Use this checklist to organize the local steps and the board’s records. Confirm any unclear requirement with the responsible building department.
- Confirm whether the building is in unincorporated Palm Beach County or a city with its own building department.
- Find the certificate of occupancy date.
- For the county program, confirm whether the building is within 3 miles of a coastline.
- Keep the written notice and record the applicable deadline.
- Confirm the 180 day phase one window after written notice.
- Hire a Florida-licensed architect or engineer.
- Schedule phase one and provide the access discussed with the engineer.
- Confirm the required ePZB Building Reference ID if the county program applies.
- Review phase one findings with the engineer and determine whether phase two is required.
- For substantial structural deterioration identified in phase two, track the agency's report receipt date and the 365 day repair-start requirement.
Frequently Asked Questions
No. It applies to buildings three habitable stories or more in height that are subject in whole or in part to residential condominium or residential cooperative ownership. Single-family, two-family, three-family and four-family dwellings with three or fewer habitable stories above ground are excluded.
In unincorporated Palm Beach County, the first inspection is at 25 years within 3 miles of a coastline. Beyond 3 miles, it is at 30 years, with inspections every 10 years after. Cities run their own programs, so confirm the applicable trigger with the city building department.
Phase one must be completed within 180 days of the written notice. The local enforcement agency may extend the deadline for good cause. The owners must have an engineer or architect contract, and the inspection must be unable to be completed in time.
Phase two is required if phase one finds substantial structural deterioration. It may involve destructive or non-destructive testing. If phase one finds no signs of substantial structural deterioration, phase two is not required.
Repairs for substantial structural deterioration found in a phase two report must commence within 365 days after the local enforcement agency receives the report. Keep that receipt date in the board’s records.
The architect or engineer who prepared the report uploads it through the county online portal, ePZB. A Building Reference ID is needed. Boards can call 305-890-6333 to discuss scheduling and next steps.